Division Street sewer upgrade project almost complete
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 6 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | February 18, 2025 1:15 AM
MOSES LAKE — A project to upgrade a sewer lift station on South Division Street in Moses Lake is in the final stages.
The project was started last spring, said Lynne Lynch, Moses Lake communications and marketing specialist. Project cost as of Jan. 31 was about $774,000.
The work involved decommissioning the existing lift station equipment and materials, according to the city website; that section was completed in summer 2024. Crews also installed a new wet well, valve vault, pumps and electrical and telemetry panels.
“We are upgrading the capacity and replacing (a) decades-old pumping system and controls,” Lynch wrote in response to an email from the Columbia Basin Herald.
A detour through the left lane for southbound traffic has been in effect off and on throughout the project.
“Final testing is scheduled to begin (about Feb. 14). Then we can get the bypass pumping removed and remove the traffic control. Final cleanup will be completed soon after,” Lynch said.
The site is near a wetland, and the location contributed to the time it took to complete the project.
“There were delays due to waiting for several months for necessary electrical components that were not immediately available and difficulties with groundwater intrusion into existing manholes and vaults,” she said.
ARTICLES BY CHERYL SCHWEIZER
Road projects on hold for Labor Day weekend
MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.
Cost estimates for water source alternatives given to Moses Lake City Council
Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient
MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.
Dryer vent cleaning is important -- but often overlooked
MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.