Construction starts on Quincy Aquatic Center
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 5 months, 3 weeks AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 30, 2025 5:54 PM
Key points:
Parking at Quincy’s East Park will be limited due to construction of the new Quincy Aquatic Center. Crews are beginning site excavation.
Quincy City Council awarded a $15.7 million contract to Chervenell Construction, Kennewick.
Completion scheduled for June 2026.
QUINCY — The main parking lot for East Park in Quincy will close to traffic this week as construction crews start working on the new Quincy Aquatic Center. Russ Harrington, parks and recreation director, said crews are already excavating the site.
“They’re already ripping some of the ground up,” Harrington said.
Quincy City Council members approved a $15.7 million contract with Chervenell Construction, Kennewick, for the project at the June 3 meeting. Construction is scheduled to take about a year.
“The plan is we’ll be able to open it for our summer swim season next year,” Harrington said.
Quincy City Engineer Ariel Belino told council members the city has a plan in case the opening is delayed.
“We’re going to maintain the existing pool. Once the new pool is built, that’s the time they’re going to go back and demolish the old one,” Belino said.
The new aquatic center will have a zero-depth entry and a Lazy River, along with a six-lane swimming pool. Two to three waterslides are planned. They will be built on a separate tower and will not empty into the main pool, Harrington said. The pool will be about the same size as the existing facility, he said, but with the design, there’s more room for swimming.
The new pool will have a new entrance, locker rooms and a concession stand.
The new pool will have a stainless-steel shell covered with a lining, Harrington said. The shell is scheduled for delivery by August, with installation in September.
“Stainless steel panels get welded together, then braced up (with) backfill behind it,” he said.
The new location is above the water table, which will reduce the possibility of damage to the shell, he said.
Construction crews are also planning to pave the new parking lot prior to winter, he said. If those two things are finished, the project will be much less dependent on the weather in the spring.
The pool entrance still will be off F Street Southeast, Harrington said, but will be moved slightly further west.
Building the new pool required moving a softball field, the only softball field in town with lights. The softball field will be relocated across town to Lauzier Park, which is scheduled for additional upgrades.
The park is on 13th Avenue Southwest; the street will be widened and rebuilt, and access will be added from R Street Southwest and a new street, T Street Southwest. Lauzier Park will be the home of the new indoor sports complex known as the QPlex. It’s in the process of design.
ARTICLES BY CHERYL SCHWEIZER
Three arrested in Royal City area thefts case
ROYAL CITY — Three men were arrested and booked into the Grant County Jail on suspicion of possessing stolen property after a search was served on a home near Beverly Thursday.
More park improvements planned for Royal City in ‘26
ROYAL CITY — Lions Park in Royal City now has a soccer field, so city officials will be working on the next phase of improvements in 2026. The first phase of upgrades to Apple Avenue also is scheduled for 2026, and both are among the projects reflected in the city’s 2026 budget. The budget was approved by Royal City City Council members Tuesday.
Sleep Diagnostic Center physician pleads guilty to Medicaid fraud
Charges involve charging Apple Health for recalled, altered CPAP devices
BREWSTER — A Brewster physician who operates a sleep diagnostic clinic in Moses Lake and Wenatchee will be sentenced March 24 as part of a Wednesday plea deal on Medicaid fraud charges.