Construction starts on Quincy Aquatic Center
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 2 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 30, 2025 5:54 PM
Key points:
Parking at Quincy’s East Park will be limited due to construction of the new Quincy Aquatic Center. Crews are beginning site excavation.
Quincy City Council awarded a $15.7 million contract to Chervenell Construction, Kennewick.
Completion scheduled for June 2026.
QUINCY — The main parking lot for East Park in Quincy will close to traffic this week as construction crews start working on the new Quincy Aquatic Center. Russ Harrington, parks and recreation director, said crews are already excavating the site.
“They’re already ripping some of the ground up,” Harrington said.
Quincy City Council members approved a $15.7 million contract with Chervenell Construction, Kennewick, for the project at the June 3 meeting. Construction is scheduled to take about a year.
“The plan is we’ll be able to open it for our summer swim season next year,” Harrington said.
Quincy City Engineer Ariel Belino told council members the city has a plan in case the opening is delayed.
“We’re going to maintain the existing pool. Once the new pool is built, that’s the time they’re going to go back and demolish the old one,” Belino said.
The new aquatic center will have a zero-depth entry and a Lazy River, along with a six-lane swimming pool. Two to three waterslides are planned. They will be built on a separate tower and will not empty into the main pool, Harrington said. The pool will be about the same size as the existing facility, he said, but with the design, there’s more room for swimming.
The new pool will have a new entrance, locker rooms and a concession stand.
The new pool will have a stainless-steel shell covered with a lining, Harrington said. The shell is scheduled for delivery by August, with installation in September.
“Stainless steel panels get welded together, then braced up (with) backfill behind it,” he said.
The new location is above the water table, which will reduce the possibility of damage to the shell, he said.
Construction crews are also planning to pave the new parking lot prior to winter, he said. If those two things are finished, the project will be much less dependent on the weather in the spring.
The pool entrance still will be off F Street Southeast, Harrington said, but will be moved slightly further west.
Building the new pool required moving a softball field, the only softball field in town with lights. The softball field will be relocated across town to Lauzier Park, which is scheduled for additional upgrades.
The park is on 13th Avenue Southwest; the street will be widened and rebuilt, and access will be added from R Street Southwest and a new street, T Street Southwest. Lauzier Park will be the home of the new indoor sports complex known as the QPlex. It’s in the process of design.
ARTICLES BY CHERYL SCHWEIZER
Road projects on hold for Labor Day weekend
MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.
Cost estimates for water source alternatives given to Moses Lake City Council
Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient
MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.
Dryer vent cleaning is important -- but often overlooked
MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.