Sunday, July 13, 2025
84.0°F

Bigfork Bridge truss to be placed April 1

Bigfork Eagle | UPDATED 3 months, 2 weeks AGO
| March 26, 2025 12:00 AM

St. Patrick’s Day brought the delivery of the new Bridge Street Bridge truss to the project site on Monday, March 17.

The Montana Department of Transportation and Battle Ridge Builders have already begun assembling the truss. Each side will be assembled and placed separately on the new foundation, spanning the Swan River. Once they are placed, crews will connect them and install the remaining pieces. 

Placement of the side pieces is expected to occur on Tuesday, April 1.

Other work planned includes pouring concrete for the retaining wall on the north side of the river, as well as some excavation work.
All work is subject to change due to weather and other unforeseen circumstances.
Crews will be onsite Monday through Friday from 7 a.m. to 5 p.m. 

For the latest view of the project visit bit.ly/BridgeSt-Camera.

MORE LOCAL-NEWS STORIES

Friday Senior Bowlers — Feb. 21, 2025
Bonner County Daily Bee | Updated 4 months, 2 weeks ago
Friday Senior Bowlers — Jan. 10, 2025
Bonner County Daily Bee | Updated 6 months ago
Friday Senior Bowlers — Dec. 20, 2024
Bonner County Daily Bee | Updated 6 months, 3 weeks ago