Grant PUD places limits on electrical demand from data centers
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 31, 2025 2:00 AM
EPHRATA — Limits will be implemented on the growth of demand from data centers that get their power from the Grant County Public Utility District. Load growth limits may be applied to other large industrial customers, depending on how much power they’re requesting.
Andy Wendell, PUD senior manager of large power solutions, said the cap addresses a physical problem, which is that anticipated demand would exceed the capacity of the actual electrical distribution system, such as transmission lines.
“If we allow that growth to happen at the pace we’re hearing from our customers, we’re going to have some significant problems in our transmission system, including concerns with reliability,” Wendell said.
The PUD routinely asks customers for their estimates of future power demand, part of a process called load growth forecasting. It’s done periodically throughout the year, and Wendell said the last forecast included the possibility of a lot more demand.
“With the onset of (artificial intelligence) and other computing space, we have realized a significant increase in demand for energy from primarily our data center customers,” he said. “We started to observe that in late 2024 and certainly into this year.”
Wendell said the challenge to the transmission system is entirely separate from the question of supply. The PUD receives about 63% of the electricity generated by the Wanapum and Priest Rapids dams. Utility district officials have long projected that the PUD will use all of its share by 2026. But the PUD would have a challenge with the transmission system irrespective of the supply problem, he said.
“The generation (and) energy sources are really a separate issue,” Wendell said. “The issue at hand today is being able to transmit that from the source, which is the Columbia River grid in most cases, out to the load center, which in this case is Quincy.”
As of now, the challenge is limited to data centers.
“This is really limited to our industrial customers. The PUD is still able to allow growth in other customer classes, such as commercial, residential, ag, irrigation and other areas. We’re not hanging a sign on the door that says, ‘We’re closed for business.’”
There’s still a little room for data centers to grow, he said, and they can continue their current operations.
“We’re not asking our customers to curtail load, (to) reduce load. In all cases, our load limits give them an opportunity to grow between what they’re consuming today and where that load limit is. There’s still some growth potential in there for those customers,” Wendell said.
There’s not a lot of room left, though.
“We really anticipate folks hitting those caps in the third and fourth quarter of 2025, based on what they’ve signaled,” Wendell said.
The PUD is working on additional transmission capacity, including a new high-capacity line from Wanapum Dam to Quincy, he said. Those are long-term projects – the line to Quincy is projected for completion in 2029. Another is scheduled for completion in 2027.
“It just takes a long time to build those transmission lines, to permit them, to get the land use rights, easements, the materials and labor to construct them are years and years in the planning. They just don’t happen overnight,” he said. “That’s the challenge with them.”
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.