Friday, April 03, 2026
48.0°F

Moses Lake port to open new maintenance facility

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 10 months, 3 weeks AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | May 13, 2025 3:02 AM

MOSES LAKE — Port of Moses Lake commissioners will cut the ribbon on a new $1.4 million building May 27. The new maintenance building will replace an existing structure, and Commissioner Darrin Jackson said replacement is overdue.  

“If there was one building that needs to go away, it was that one,” Jackson said of the old facility. “Before it falls over.” 

The cost was higher than initially estimated; additional electrical work was needed as well as work to meet updated building codes.  

The new maintenance facility is one of a number of projects at the port, some completed, some nearing completion, some in the planning stages. Commissioners approved an agreement to begin testing on the roof of a section of the airport control tower.  

Facilities Director Milton Miller said it’s leaking.  

“The port owns the TRACON facility, which is the radar (section),” Miller said. “We’re looking to replace that roof this summer.” 

The testing will determine if the underlayers are damaged, and if so, how much. Cost for the testing will be about $3,200. The cost of the actual roof replacement is still to be determined.  

Commissioners accepted completion of a project to repair the canopy leading into the airport terminal, a project that had been long in the making.  

“How long — two-plus years?” Jackson asked.  

Construction challenges contributed to the delay. The curved canopy, its pillars covered in stucco, had been damaged and was in need of repairs. The roof was not part of the original project, so the contract had to be amended, something commissioners did at the May 12 meeting. 

The total project cost was just under $76,000. 

ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.