Geothermal, academic complex building in progress at CWU

NANCE BESTON | Hagadone News Network | UPDATED 1 month, 1 week AGO
by NANCE BESTON
Staff Writer | October 24, 2025 3:50 AM

ELLENSBURG — Central Washington University is enhancing its campus infrastructure with the construction of the new North Academic Complex. Spanning 108,000 square feet, this building is expected to serve as a hub for social sciences, housing general classrooms, an auditorium and dedicated spaces for the Law and Justice program, slated for completion in fall 2026. 

The NAC, which is being constructed in the north-central area of campus, marks a significant departure from CWU's typical focus on STEM-related projects.  

Delano Palmer, the Director of Capital Planning and Projects at CWU, expressed the importance of this initiative in diversifying the university's capital investments.  

“This is the first time in a long time that we've been able to dedicate resources to a non-STEM-related project,” Palmer said. “With substantial enrollment growth projected, this facility will provide much-needed classroom space and foster a sense of community among our students.” 

Currently, the university is replacing two older buildings – the L&L Building, which has already been demolished, and Carroll Hall, set for demolition next year. By doing so, CWU aims to modernize its academic offerings while expanding its educational environment to accommodate increasing numbers of freshmen.  

“This project is crucial for enhancing students’ experiences and creating inviting, functional spaces that support modern learning methodologies,” Palmer said.  

Among the notable features of the NAC is a 240-seat TED Talks-style auditorium designed for lectures and community events.  

“This auditorium will be one of the largest on campus and equipped with state-of-the-art technology," Palmer said. "We envision that it will become a key venue for not only student events but also public discourse and outreach programs.” 

The design of the NAC prioritizes sustainability and resource efficiency, aligning with Washington State’s Climate Commitment Act, according to CWU officials. The new building will utilize a geothermal heating and cooling system, leveraging the renewable heat from the Ellensburg Aquifer through a dedicated GeoEco Plant.  

“Once operational, this system will connect to 500,000 square feet of academic space across campus, reinforcing our commitment to sustainable building practices,” Palmer said.  

He said this initiative distinguishes CWU as a leader in sustainable education facilities compared to other universities in Washington. 

In addition to geothermal technology, the NAC will feature skylights and large-pane windows throughout the structure to take advantage of the natural light. Palmer indicated that this was an intentional design choice to enhance student well-being and comfort.  

“We believe a well-lit environment fosters creativity and collaboration, essential elements for our students' success,” he said. 

Cross-laminated timber sourced from local tribal nations will also play a prominent role in the building’s design.  

“This unique choice not only brings aesthetic beauty to the structure but also supports local economies and reinforces our partnership with the Yakama Nation,” Palmer said.  

The project timeline indicates that the NAC construction began in September 2023, with the initial phase concluded this year, followed by the installation of furnishings and equipment. The building is anticipated to be fully operational by fall 2026 

“We aim for our faculty to move in during the summer of 2026, ready to welcome students for the following fall semester,” he said. 

    The exterior of the new North Academic Complex building at Central Washington University. The complex will be around 108,000 square feet and is set to open by the fall of 2026.
 
 
    The new Central Washington University North Academic Complex building features wooden accents. The cross-laminated timber was sourced from local tribal nations and facilitated by Yakama Forest Products.
 
 
    Central Washington University Capital Planning and Projects Director Delano Palmer said the North Academic Complex is on schedule and on budget as of this far.
 
 


ARTICLES BY NANCE BESTON

Mayor Peter Sharp takes oath of office
December 5, 2025 1:15 a.m.

Mayor Peter Sharp takes oath of office

SOAP LAKE – Grant County Commissioner Kevin Burgess adminstered the oath of office to Mayor Peter Sharp Wednesday. Sharp was previously appointed to this role at the Sept. 18, 2024, council meeting after his predecessor Allen DuPay quit during the Aug. 7, 2024, meeting.

Newhouse, colleagues introduce infrastructure bill
December 4, 2025 4:55 p.m.

Newhouse, colleagues introduce infrastructure bill

WASHINGTON D.C. — On November 21, 2025, a bipartisan coalition of lawmakers introduced the Urban Canal Modernization Act, HR 6279, aimed at addressing the deteriorating condition of urban canal infrastructure across the country. This legislation, sponsored by Representatives Dan Newhouse, R-WA; Mike Simpson, R-ID; Adam Gray, D-CA; and Russ Fulcher, R-ID focuses on providing federal support for the extraordinary operation and maintenance of urban canals deemed to be at significant risk of failure. “As communities in Grant County and elsewhere face serious risks from aging canal systems, it is imperative that we act now to ensure vital water infrastructure is maintained and upgraded,” Newhouse wrote in a statement. “The Bureau of Reclamation’s canals are in dire need of repairs, and the surrounding communities who rely on them would be at risk if they were to fail. This legislation provides local authorities with additional resources to manage these critical pieces of infrastructure while protecting the people and property around canals of concern.”

Ephrata water tower waiting for final tests
December 3, 2025 6:30 p.m.

Ephrata water tower waiting for final tests

EPHRATA — The City of Ephrata is still waiting for the final testing to come back to the water tower. The city had originally hoped the tower would be connected to the water system by Thanksgiving; however, the intensive water testing is taking longer than anticipated.