Shell of new Quincy pool scheduled to arrive this month
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 6 months, 4 weeks AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | September 6, 2025 3:48 PM
QUINCY — While it’s not scheduled to open until next summer, the new Quincy Aquatic Center will really start taking shape this fall. Construction crews started excavating the site in July, and Quincy Parks and Recreation Director Russ Harrington said there’s been a lot of progress below ground level.
“I think all the concrete pours for underground are done,” Harrington said.
Chervenell Construction out of Kennewick was awarded a $15.7 million for the construction of the pool, with completion scheduled in June 2026. Some of the progress is visible from F Street Southwest, where walls are going up for the front entrance, equipment rooms, locker rooms and a concession stand. Crews are also working on the concrete base for the new pool. The pool is a metal shell with a lining, and the panels that will make up the shell are scheduled to start arriving sometime this month, Harrington said.
“It gets shipped over from Italy,” he said, and is welded together onsite. Backfilling is part of the installation, of course, and the contractor, Chervenell Construction, Kennewick, is working to get all that done before cold weather and frost make that task impossible.
Because that’s a lot of metal and a lot of water, the underground concrete base is getting close and careful attention.
“It has to be well-prepared to drop in a very weighty object like a pool,” said Quincy City Administrator Pat Haley.
Quincy City Council members approved changes to the contract Sept. 2 at the request of City Engineer Ariel Belino. The site is close to the water table, he said, and additional water barriers were needed to protect the concrete.
Construction crews are also working on the new parking lot, with the goal of laying down the asphalt in October.
“If they can get that done, they should be sitting in a good spot,” Harrington said. “The weather – that's the key.”
Relocation of a fiber conduit caused a short delay, Haley said, but otherwise the project is on schedule.
“The contractor makes the most money when things are done in the shortest amount of time,” Haley said.
Attendance for the last season of the existing pool was a little lower than in 2024, Harrington said, but until poor weather conditions hit in August, attendance was running ahead of last year. He said he thought that was due in part to interest in the new pool.
“There are a lot of people we talked to who grew up with this pool. And there were a lot of people coming over (to go to the pool) and bringing their families, because this was the last chance they’re going to get,” he said.
Work on the entrance building is projected to continue over the winter. Harrington said the visible progress is sparking a lot of interest.
“Everybody is getting excited,” he said.
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.