Thursday, March 19, 2026
39.0°F

North Boyer Road reopening delayed to late fall

JACK FREEMAN | Hagadone News Network | UPDATED 5 months, 3 weeks AGO
by JACK FREEMAN
| September 23, 2025 1:00 AM

SANDPOINT — Progress on the North Boyer Road culvert has stalled as crews await a custom fitted pipe to be delivered, according to Sandpoint Public Works Director Holly Ellis.

Ellis said that the pipe is expected to be delivered from the manufacturer in South Dakota sometime between the middle of October to the middle of November. Once the pipe arrives, construction will begin immediately and take approximately two to three weeks to finish, Ellis said.  

"We were in communication as recently as this morning on the productivity and construction of the pipe,” Ellis said at the Sept. 17 City Council meeting. “Unfortunately, how we manufacture in the U.S. today, everything is made to order. So we are in line, waiting for our aluminum pipe to be bent and built.”  

Sandpoint Mayor Jeremy Grimm said at the Sept. 17 meeting that there are only two manufacturers in the country who make custom culvert pipes at the required size. Ellis had previously given an expected reopening date of late September, but due to the waitlist of these companies, that date is no longer feasible. 

At the Sept. 3 meeting, Grimm said that the city did not have a final price on the repairs and that the city may need to apply for disaster aid and financial support from Bonner County and the state of Idaho. In July, Ellis told the Daily Bee that the city had made $250,000 available from its reserves to fund the emergency project.  

Construction will not begin without the pipe, which is the last item needed by the city. Ellis told the Daily Bee on Aug. 7 that once the materials arrive, crews from Advanced Dirt Works will begin by removing the asphalt, water and rock away from the area.  

The section of North Boyer Road just after the fairgrounds was closed in early June, shortly after the city identified that the culvert’s condition was rapidly deteriorating. The city of Sandpoint declared the culvert failure as an emergency later in early July. 

Throughout the repair process, Ellis has stated that the city understands that the road is critical infrastructure during the winter season and is moving as fast as crews can to replace it.  

"We have all the Earthwork and contractors ready to go as soon as that culvert arrives,” Grimm said at the council’s Sept. 3 meeting. “We appreciate the patience of the public and those up on Schweitzer as we work to repair that emergency.” 

ARTICLES BY JACK FREEMAN

U.S. Army Corps of Engineers to spend $20 million to replace Albeni Falls Dam spillway gates
March 19, 2026 1 a.m.

U.S. Army Corps of Engineers to spend $20 million to replace Albeni Falls Dam spillway gates

The United States Army Corps of Engineers has awarded a $20 million contract to Knight Construction and Supply that will see all 11 spillway gates at thee Albeni Falls Dam replaced, according to a Wednesday press release.

City to host downtown revitalization open house
March 18, 2026 1 a.m.

City to host downtown revitalization open house

City staff will be holding an open house in Sandpoint Community Hall next week to provide an updated design and gather public input on the Downtown Revitalization Phase No. 3 project.

Learning ignites at SHS science circuit
March 15, 2026 1 a.m.

Learning ignites at SHS science circuit

Inside Sandpoint High School’s gym, elementary school students inflated cow lungs, flinched at bowling balls and made bubble tea boba as a part of the annual Science Circuit.