Shifting traffic lanes planned along I-90 in Hansen Road construction zone
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 months, 3 weeks AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 7, 2026 1:40 AM
MOSES LAKE — At least for a while, drivers at the Hansen Road intersection on Interstate 90 probably won’t face delays but will be working their way through the construction zone.
Demolition of the old Hansen Road overpass is complete, with the overpass and its supports removed. With the old bridge out of the way – literally – freeway drivers will be experiencing 24/7 single lane closures. Summer Derrey, communications manager for the Washington Department of Transportation North Central region, said different lanes will be closed at different times.
“Shifts will occur as needed, depending on the work taking place,” Derrey said.
The changing construction zone means local access is subject to change. The eastbound offramp at Hansen Road was closed while crews worked on the south end of the bridge but reopened once they moved to the north end.
Drivers are conducted through the construction zones with the aid of temporary signs and a lot of big orange barrels. Speeds are reduced in the construction area.
The bridge is being replaced due to extensive damage discovered during an inspection in January. The bridge was closed to traffic, and DOT officials eventually decided to replace rather than repair it. The new bridge is scheduled to open in late 2026 or early 2027.
An inspection of the Adams Road overpass east of George at about the same time found extensive damage there too. The inspection followed the discovery of a hole in the bridge deck, and it’s been closed since early March.
The overpass is scheduled for replacement in 2027, which is why there was a drilling rig at the south end of the bridge for a few days this week. Department of Transportation employees were obtaining subsoil samples, Derrey said.
“Crews are testing the stability of the ground,” she said.
Some projects are done or almost done, it being August and more than halfway through the construction season. One of the almost-done ones is on North Stratford Road in Moses Lake.
Construction crews have been replacing a water main that extended, among other places, over the Alder Street bridge. The water line was embedded in the bridge, and it required cutting a section of the street to access it. That required single lane closures in the construction zone.
That project was scheduled to be completed tomorrow, but the city’s engineering department said repaving the sections of road is scheduled for early next week. Once that’s done, the project is finished.
ARTICLES BY CHERYL SCHWEIZER
Lodging tax money to be used to upgrade Larson, Lauzier playfields and other projects
MOSES LAKE — Fields in Lauzier Park and some at the Larson Playfields will get upgrades with money generated by the city's lodging tax. Those were at the top of a list of projects recommended by the city's lodging tax committee and approved by the Moses Lake City Council Oct. 27.
Samaritan hospital use up from 2025, but below 2026 budget expectations
MOSES LAKE — While Samaritan Hospital is a little busier in 2026 than 2025, patient utilization is less than projected in 2026 budget through the first three quarters of the year. Chief Financial Officer Darryl Wolfe said inpatient revenue was about 6% below the budget projection for the year to date, and about 12% below the projected revenue for September. Revenues were higher than budget projections in May, June and August, but lower than projections during the rest of the year. As of the end of September, Samaritan had a net loss of about $3.4 million for the year. The 2026 budget projected a year-to-date loss of about $456,700 through September.
Conservation district receives $9.23 million grant for OGWRP project
MOSES LAKE — Construction will start sometime this winter on a project to convert additional acreage from groundwater irrigation to surface water in a section of Grant County.