City unveils engagement plan for Downtown Revitalization Phase No. 3
JACK FREEMAN | Hagadone News Network | UPDATED 1 day, 20 hours AGO
SANDPOINT — City staff revealed their public engagement plan for the Downtown Revitalization Phase No. 3 at last Wednesday’s City Council meeting.
The plan features two open houses held by the city, with the first scheduled for March following the completion of the 30% design drawings. This open house was moved at the request of council to allow the public to give their input while the project was still in the early design phase.
“We expect the 30% drawings in early February, and we're hoping to have our first public open house within a few weeks after that,” Project Manager Erik Bush said. “That'll allow us to present that here at City Council and then be able to get feedback from the community at large.”
The second open house is scheduled for this summer, following the completion of the 90% design drawings. Bush said that scheduling is purposeful so that the designs can incorporate feedback from the public quickly before the city begins construction, which staff expect to happen in September.
Before that can begin, representatives from The Langdon Group, the city’s contracted outreach firm, will be interviewing key stakeholders in the project footprint and downtown. Bush said the city staff will not be involved in these interviews to allow the interviewees to be honest about their feelings on not only the third phase, but how the city did on the first and second phases.
In addition, the city will be forming a technical advisory group composed of members of the city’s committees and other identified stakeholders. This group is scheduled to meet three times this year, corresponding with the public open houses, until construction begins.
“We're trying to kind of grab all the comments, all the impact that we can with those two structures,” Bush said. “I'll always be available for questions from you all, from the any member of the community.”
Once the engagement plan begins in March, TLG will launch a project website with more information and images for the public, similar to the city’s efforts with the wastewater treatment plan bond. Bush said city staff would also be attending community events, like the Sandpoint Farmers’ Market, to get the word out about the project.
The third phase of the Downtown Revitalization project will span from Church Street to at least Lake Steet on First Avenue. The project is set to widen sidewalks, improve street furniture and landscaping, provide parking upgrades, address stormwater treatment issues and bring more public art installations.
“I definitely think that more communication with the public is better,” Councilor Kyle Schreiber said. “The last thing we want is to get to the finish line and have the public not support we come up with.”
ARTICLES BY JACK FREEMAN
Priest River Elementary evacuated Monday
Students and staff were evacuated from Priest River Elementary Monday morning over concern about a potential propane leak.
Grants to provide fresh produce for LPOSD and WBCSD students
Elementary school students in the Lake Pend Oreille and West Bonner School District will continue to explore fresh fruit and vegetables thanks to state-issued grants.
Police apprehend suspect following standoff
Sandpoint Police along with the Bonner County Sheriff's Office and U.S. Marshalls closed off the 1200 block of Cedar Street for four hours on Monday.