No more ‘ruts and bumps’ as Polson Airport finalizes runway revamp

EMILY MESSER | Hagadone News Network | UPDATED 3 weeks, 5 days AGO
by EMILY MESSER
Emily Messer joined the Lake County Leader in July of 2025 after earning a B.A. degree in Journalism from the University of Montana. Emily grew up in the rolling hills of southeast Missouri. She's lived in Montana since 2022 and honed her reporting craft through the UM J-School newspaper and internships at the RMEF Bugle Magazine and the Missoulian. At the Leader, she covers government, business, education, agriculture and community news. Contact Emily Messer at [email protected] or 406.883.4343 | June 18, 2026 12:00 AM

At the Polson Airport, a $6.8 million entire airport upgrade is underway, all being completed in a planned 90-day window with the projected construction wrapping on July 2.  

The project, 95% covered by about a $6.4 million Federal Aviation Administration grant, includes reconstructing the runway, parallel taxiway and apron. The infrastructure improvements also entail a new lighting system, new wind cones and a new set of approach lights on the southern end of the airport. A portion of the funding for this upgrade also comes from a Montana Aeronautics grant.  

Mat Wilder, the project manager with Robert Peccia & Associates, based in Helena, said this will set the airport up for the next 20 years, with only basic maintenance needed.  

RPA designed and bid this project to take only 90 days and awarded the contract to Knife River. During this period, the airport has been entirely closed to air traffic. The upgrades were originally projected to be completed by June 27, but Wilder said the weather has caused some delays.  

RPAs' design fees, onsite inspections and airport surveys will also be covered by the grant.  

Forrest Walker, the engineering designer and construction technician with RPA, explained that some of the previous asphalt was in good enough condition that they were able to pulverize it and will create a new paved top over it.  

In other areas, crews had to cut into the ground by 34 inches or more to create a stable base layer. Wilder said there were also portions where crews had to dig another two feet into the ground, due to the amount of clay. This meant they had to bring in more gravel and made the design “pretty challenging.”  

Wilder explained that the previous pavement had cracked. The subgrade was also starting to heave, and during the wintertime, this caused ruts and bumps to appear in the pavement.  

Wilder said Knife River has been great to work with, and when they are feeling behind, they have added more men and equipment at the airport to get back up to speed. 

The project also included replacing the entire drainage system beneath the runway to prevent water from saturating the materials beneath the pavement.  

“Some of the drain edging (a specialized barrier around landscaping) drainpipes we put in, they have a grade of 2%,” Walker said. “Turns out an airport's a big flat chunk of ground, and big flat chunks of ground are hard to drain water off of.”  

Wilder said the dimensions of the new pavement are not changing. However, some of the corners are being widened to meet FAA standards.  

The 4,194-foot-long runway is built to accommodate general aviation aircraft weighing up to 12,500 pounds.  

Wilder said that airport users have been understanding, even though the airport shutdown has been an inconvenience. He added that the Lake County Joint Airport Board has also been great to work with and is very supportive.  

“Our biggest focus was to get this knocked out before the peak tourist season, before peak flying season,” Wilder said. 

The airport also received another grant, which they are using to fund an eight-foot wildlife fence project around the entire airport. Wilder said this project is only in its preliminary phases, and they hope to bid it out this summer or in early fall.   Project manager Mat Wilder and engineering designer and construction technician Forrest Walker, both with Robert Peccia & Associates, review the airport revamp plans. (Emily Messer/Leader)

ARTICLES BY EMILY MESSER

Looking Forward: A Note from Your New Editor
July 9, 2026 midnight

Looking Forward: A Note from Your New Editor

I would like to take this opportunity to officially introduce myself. My name is Emily Messer, and I am honored to be taking on the role of editor at the Lake County Leader.

Charlo celebrates America’s 250th birthday with a show out parade
July 9, 2026 midnight

Charlo celebrates America’s 250th birthday with a show out parade

Last weekend, the community of Charlo came together for their annual Fourth of July parade, and this year was full of red, white and blue with candy flying in the air as the parade headed down the packed streets of Charlo.

Red, white and blue light up Polson’s sky on Fourth of July Eve
July 9, 2026 midnight

Red, white and blue light up Polson’s sky on Fourth of July Eve

Polson Chamber of Commerce kicked off the Fourth of July weekend celebration of the “Big 250” with lights in the sky on July 3, viewed from the hot spot location on the riverside and from a newfound location.