No more ‘ruts and bumps’ as Polson Airport finalizes runway revamp

EMILY HEIMARK | Hagadone News Network | UPDATED 4 months, 1 week AGO
by EMILY HEIMARK
Emily Heimark (Messer) joined the Lake County Leader in July of 2025 after earning a B.A. degree in Journalism from the University of Montana. Emily grew up in the rolling hills of southeast Missouri. She's lived in Montana since 2022 and honed her reporting craft through the UM J-School newspaper and internships at the RMEF Bugle Magazine and the Missoulian. At the Leader, she covers government, business, education, agriculture and community news. Contact Emily Heimark at [email protected] or 406.883.4343 | June 18, 2026 12:00 AM

At the Polson Airport, a $6.8 million entire airport upgrade is underway, all being completed in a planned 90-day window with the projected construction wrapping on July 2.  

The project, 95% covered by about a $6.4 million Federal Aviation Administration grant, includes reconstructing the runway, parallel taxiway and apron. The infrastructure improvements also entail a new lighting system, new wind cones and a new set of approach lights on the southern end of the airport. A portion of the funding for this upgrade also comes from a Montana Aeronautics grant.  

Mat Wilder, the project manager with Robert Peccia & Associates, based in Helena, said this will set the airport up for the next 20 years, with only basic maintenance needed.  

RPA designed and bid this project to take only 90 days and awarded the contract to Knife River. During this period, the airport has been entirely closed to air traffic. The upgrades were originally projected to be completed by June 27, but Wilder said the weather has caused some delays.  

RPAs' design fees, onsite inspections and airport surveys will also be covered by the grant.  

Forrest Walker, the engineering designer and construction technician with RPA, explained that some of the previous asphalt was in good enough condition that they were able to pulverize it and will create a new paved top over it.  

In other areas, crews had to cut into the ground by 34 inches or more to create a stable base layer. Wilder said there were also portions where crews had to dig another two feet into the ground, due to the amount of clay. This meant they had to bring in more gravel and made the design “pretty challenging.”  

Wilder explained that the previous pavement had cracked. The subgrade was also starting to heave, and during the wintertime, this caused ruts and bumps to appear in the pavement.  

Wilder said Knife River has been great to work with, and when they are feeling behind, they have added more men and equipment at the airport to get back up to speed. 

The project also included replacing the entire drainage system beneath the runway to prevent water from saturating the materials beneath the pavement.  

“Some of the drain edging (a specialized barrier around landscaping) drainpipes we put in, they have a grade of 2%,” Walker said. “Turns out an airport's a big flat chunk of ground, and big flat chunks of ground are hard to drain water off of.”  

Wilder said the dimensions of the new pavement are not changing. However, some of the corners are being widened to meet FAA standards.  

The 4,194-foot-long runway is built to accommodate general aviation aircraft weighing up to 12,500 pounds.  

Wilder said that airport users have been understanding, even though the airport shutdown has been an inconvenience. He added that the Lake County Joint Airport Board has also been great to work with and is very supportive.  

“Our biggest focus was to get this knocked out before the peak tourist season, before peak flying season,” Wilder said. 

The airport also received another grant, which they are using to fund an eight-foot wildlife fence project around the entire airport. Wilder said this project is only in its preliminary phases, and they hope to bid it out this summer or in early fall.   Project manager Mat Wilder and engineering designer and construction technician Forrest Walker, both with Robert Peccia & Associates, review the airport revamp plans. (Emily Messer/Leader)

ARTICLES BY EMILY HEIMARK

October 22, 2026 midnight

Proposed changes to City of Polson government to appear on ballot

The Polson Local Government Review Study Commission completed its report earlier this year, and the proposed changes to the city charter and supplementary report of action to be taken will appear on the November ballot.

Native cowboy from Mission Valley travels to Kyrgyzstan for Nomad World Games
October 18, 2026 midnight

Native cowboy from Mission Valley travels to Kyrgyzstan for Nomad World Games

Reaching down from the back of his horse, he grabs the goat carcass, a total of 80 pounds of dead weight, as dust strikes him in the face; the adrenaline rush is never-ending, and the physical demands on his body are unreal.

Rollins Fire completes community-funded addition and remodel
October 22, 2026 midnight

Rollins Fire completes community-funded addition and remodel

After outgrowing its space, the Rollins Volunteer Fire Department sought support from the community and raised $2.2 million to fund necessary upgrades and a station addition.