Hansen overpass rebuild estimated to cost $15-17 million

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 8 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 20, 2026 3:30 AM

MOSES LAKE — While a final cost hasn’t been determined, the new overpass at Hansen Road west of Moses Lake will cost an estimated $15 to $17 million. Chris Keifenheim, director for the Washington Department of Transportation, North Central Region, said Wednesday that demolition should start in June or early July.  

“Probably by the end of July or (early) August, you'll see a new bridge construction starting, and that will last until about the end of the year, when we anticipate completion,” Keifenheim said. 

He gave an update during a community meeting on the project; the bridge has been closed since mid-January due to deterioration both in the bridge deck and in the supporting structure. The closest detour route is Hiawatha Road, and Keifenheim said the contracts for Hansen Road include money to monitor the Hiawatha overpass.  

“Since we closed Hansen bridge, we said, ‘Let's take a real close look at Hiawatha.’ Hiawatha bridge is built in the same timeframe, 1958, so it is in similar condition to Hansen, but a little bit better. It's going down the same path, which isn't a great thing, but the good news is it's in a little better shape,” Keifenheim said. “We're actually including some provisions in the contract for Hansen bridge that if we need to, we can make some temporary repairs, in order to keep Hiwatha open for the duration of the detour.” 

Bridge demolition, and later some of the bridge construction, will require temporary closure of some lanes of Interstate 90 – and, said Randy Giles, WSDOT local construction engineer, complete freeway closure on a couple of occasions. 

“While we're demolishing overhead of I-90, we will have to shut I-90 down, and when we do one side, we'll put everybody over on the other (lanes), or we probably will use the westbound ramp for westbound traffic,” Giles said. “But that will be of very short duration. We expect the overhead to come down two or three days during the daytime.” 

Some of the work requiring lane closures and detours might happen at night, Giles said.  

“When we come back and set girders during the construction of the new bridge, we'll have to have a similar situation, because it's overhead work,” he said. “Now that work could probably happen at night, and that's probably what we'll do, is set that up for nighttime work.” 

Keifenheim was asked about revisions to the offramps and onramps, as long as the bridge itself was being replaced. He said the current project will only replace the bridge. While other revisions around the bridge are needed, in his opinion, the current contract is only to replace the bridge.  

In answer to a question, Keifenheim said the bridges at Broadway and Pioneer Way are both newer and in better condition than the bridges farther west. They are scheduled for regular inspections, he said. 

Dodson Road was built in the 1990s and is in better shape than Hiawatha or Hansen, Keifenheim said. But Adams Road, the next freeway overpass to the west of Dodson, was closed to traffic in early March. 

“We closed that one for basically the same situation that we're seeing out here at Hansen Road. And right now we're working through potential solutions, what exactly needs to be done, if it needs to be replaced, if it needs rehab, and then working through funding on that as well,” he said.  


ARTICLES BY CHERYL SCHWEIZER

Mattawa may eliminate one PD position, drop SRO
November 21, 2026 1:10 p.m.

Mattawa may eliminate one PD position, drop SRO

MATTAWA — The Mattawa City Council and city officials are discussing eliminating one Mattawa Police Department position and not renewing the contract with the Wahluke School District for a school resource officer. Wahluke Superintendent Andy Harlow said WSD officials and the Wahluke School Board are looking for alternatives in light of that discussion. "Right now, we want to work with the chief and the mayor and the council to get this figured out. But at this point, based on what we have, we're considering all options," Harlow said. Mayor Maria Celaya said in a text message Mattawa City Council members are discussing those options.

Consumers asked to use caution to avoid charity scams
November 20, 2026 3 a.m.

Consumers asked to use caution to avoid charity scams

MOSES LAKE — Christmas is a season of giving, and there are plenty of worthy causes out there – but there are scammers out there working to divert some of that generosity to themselves. In addition, when it comes to defrauding people, scammers aren't content to wait until the holiday season. Scammers will latch on to any incident, any natural disaster in their attempts at fraud. "When there's a disaster such as the Spokane wildfires or an incident that affects a community, such as the line of duty deaths of the two sheriff's deputies in the Spokane area, fraudsters may take may choose to take advantage of people's kindness by creating fake charity accounts," said Kyle Foreman, public information officer for the Grant County Sheriff's Office.

Public hearing Tuesday on 2027 Moses Lake municipal budget
November 20, 2026 3:20 a.m.

Public hearing Tuesday on 2027 Moses Lake municipal budget

MOSES LAKE — Moses Lake residents will have one additional opportunity to comment on the city's 2027 budget Tuesday. The final public hearing for the budget is scheduled for the Nov. 24 Moses Lake City Council meeting. The city's expenditures will exceed its revenues, but Finance Director Sheila Danielson said it was money city officials anticipated spending. "The use of fund balance is primarily related to expenditures of capital projects," Danielson wrote in response to an email from the Columbia Basin Herald. For all city departments, projected revenues will be about $127.7 million, Danielson said, with expenditures projected at about $136.8 million. Some departments will be using reserve funds, essentially money saved for those projects. Danielson estimated that would be about $9.4 million across all city departments.