Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | May 2, 2026 2:40 PM
OTHELLO — Construction begins Monday on a new roundabout near Othello, which will mean the start of flagger-controlled traffic at the intersection of State Route 17 and West Cunningham Road. Drivers going to and past Othello should plan for delays, according to a press release from the Washington Department of Transportation.
Sebastian Moraga, communications consultant for the WSDOT North Central region, said traffic control during the first week of the project will be controlled by flaggers. They'll be directing traffic during daylight hours, and West Cunningham will be open for traffic at the intersection. That changes after the first week, however.
After that, while SR 17 will stay open, West Cunningham will be closed to traffic across the intersection.
“(From) May 11, one-way alternating traffic controlled by temporary signals will remain in place, including weekends and off-duty hours,” Moraga wrote in a WSDOT press release.
Construction crews will be working from 7 a.m. to 6 p.m. Monday through Friday, Moraga said.
“The final phase of the work, striping and seeding, will occur at night with the roundabout available to travelers and flagger-controlled traffic when necessary,” Moraga said.
Project completion is scheduled for late July.
For drivers who use West Cunningham, the DOT is setting up detours with signage via Lee Road to the west of SR 17, Booker Road to the east and State Route 26 to the south.
The configuration of SR 17 will stay the same, with one southbound lane and one northbound lane. The roundabout will have a high curb and a mound of rocks in the middle.
The roundabout has been in the planning stages for about five years. Department of Transportation officials originally announced in 2021 that a roundabout would be built at that intersection in 2023.
But challenges with right of way and other issues pushed back construction, and after some delays the project was rescheduled for 2025. The DOT was building a roundabout at the intersection of SR 26 and South First Avenue, which was completed in fall 2025. The West Cunningham project was going to follow that, but a lack of funding pushed it back another year.
In 2021, DOT officials said the intersection had been identified as one with a high number of injury accidents. The analysis showed the highest number of injury accidents involved drivers crossing SR 17.
The intersection has been modified over time, with left turn lanes for northbound and southbound traffic and a right turn lane for southbound traffic. The intersection was reworked to improve sight lines, and the speed limit was reduced, but those revisions didn’t solve the problems, according to DOT officials in 2021.
ARTICLES BY CHERYL SCHWEIZER
Hermiston man sentenced in 2022 murder of Moses Lake woman
EPHRATA — A Hermiston, Oregon man has been sentenced to 20 years to life in prison following his guilty plea in the March 2022 murder of a Moses Lake woman.
Delays anticipated at Othello intersection as roundabout construction begins
OTHELLO — Construction begins Monday on a new roundabout near Othello, which will mean the start of flagger-controlled traffic at the intersection of State Route 17 and West Cunningham Road.
Road Report: Road construction starting to ramp up
MOSES LAKE — It turns out that building a more pedestrian-friendly crosswalk involves digging. A lot of digging.