Quincy Intermodal Terminal to expand
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 4 hours, 28 minutes AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | September 1, 2026 3:45 AM
QUINCY — The Port of Quincy will be expanding its intermodal rail yard. Commission chair Curt Morris said the port has an apparent low bidder for the project, but the contract award is delayed until federal rail officials give final approval for the funding.
“We should have that (approval) this week, for sure,” Morris said.
The intermodal facility allows shippers to switch from one kind of transport to another, from trucks to a train or from a train to trucks. Rail lines in the existing facility will be extended to connect with existing lines at Road O Northwest.
“It actually goes further. But the further is the second phase,” he said.
Morris said the first phase of construction would double the amount of track at the intermodal facility.
The contract also includes improvements to the railroad crossing at Road O NW, Morris said. The actual construction of the crossing will be part of the second phase, he said.
The rail line is inside the Quincy city limits, which means city officials will decide what the warning signs will be at the road crossing.
“We got the information needed, so we’ll get it designed,” Morris said.
The port has received federal funding for the first phase, he said. Funding for the second phase is pending.
The intermodal expansion is part of a larger effort to recruit businesses into Quincy, Morris said, but the transportation, water and power challenges have to be addressed first. At least one company has delayed its planned move to Quincy while the infrastructure work is ongoing.
Port officials announced in February an agreement with Colusa Indian Energy to build independent electrical generation, and the port is working with the Quincy-Columbia Basin Irrigation District to obtain additional water.
ARTICLES BY CHERYL SCHWEIZER
Quincy Intermodal Terminal to expand
QUINCY — The Port of Quincy will be expanding its intermodal rail yard. Commission chair Curt Morris said the port has an apparent low bidder for the project, but the contract award is delayed until federal rail officials give final approval for the funding. “We should have that (approval) this week, for sure,” Morris said.
Like other local districts, Quincy’s school enrollments declining
QUINCY — The trend is gradual, but it’s the same in the Quincy School District as other Columbia Basin school districts, and districts statewide – student enrollment is declining. For the 2026-27 school year, QSD officials are projecting enrollment at the equivalent of about 3,120 students, plus 48 children in the district’s transitional kindergarten class. The 2025-26 school year ended with the equivalent of 3,181 students, but the graduating senior class was considerably bigger than the incoming kindergarten class.
Grant County PUD preliminary budget released, budget hearings scheduled
EPHRATA — Grant County Public Utility District commissioners will hold two public hearings on the 2027 budget Oct. 27 at the PUD headquarters building, 30 C St. Southwest in Ephrata. Commissioners approved both the meeting schedule and filing the preliminary budget at their Aug. 25 meeting.