Ephrata advances A Street project

NANCE BESTON | Hagadone News Network | UPDATED 1 month, 1 week AGO
by NANCE BESTON
Staff Writer | September 11, 2026 3:40 AM

EPHRATA — The Ephrata City Council unanimously approved a resolution Sept. 2 authorizing a Washington State Department of Transportation agreement supplement, allowing the city to move forward with the right-of-way phase of the A Street SE Overlay Project. 

The agreement sets aside $127,464 of the project's total $987,895 budget for right-of-way work, including temporary construction easements needed to complete driveway and sidewalk improvements along the corridor. 

According to city documents, the project will add sidewalks on both sides of A Street SE, repair areas of roadway base failure and install a new asphalt overlay. Four driveways will also be modified to properly connect with the new sidewalks. 

City Project Engineer and Grant Writer Dave Bren said the council action was an important procedural step needed to keep the project moving. 

"It allowed us to move forward with the right-of-way phase," Bren said. "It's really an administrative step, but an important step." 

Bren said the project began with grant funding secured in 2024. Earlier this year, the city successfully sought additional funding to expand the project and add sidewalks to both sides of the street. 

"Earlier this year, I actually applied and got awarded to put sidewalks on both sides of the street, not just one side, but both sides," Bren said. 

The city expects to complete design and right-of-way work by the end of the year before seeking construction bids. Construction is planned for next year's construction season. 

"Our intent is to build that in the next construction season," Bren said. "The earlier you get your request for bids, the better because a lot of the contractors are trying to lock in their projects for next year, and you can get good pricing." 

City officials said the completed project will improve pedestrian access, roadway conditions and stormwater management while enhancing the appearance of the corridor for residents and businesses. 


ARTICLES BY NANCE BESTON

Gas prices ease slightly in Washington, lower prices predicted in 2027
October 19, 2026 1:52 p.m.

Gas prices ease slightly in Washington, lower prices predicted in 2027

MOSES LAKE — Gasoline prices continue to edge lower in Washington state, Grant County and Adams County, offering motorists modest relief after reaching record highs earlier this year. However, fuel costs remain significantly higher than the national average as global oil market disruptions and tight diesel supplies continue to influence prices. According to AAA data, Washington's average price for a gallon of regular unleaded gasoline stood at $5.39 on Oct. 19, down 6 cents from a week ago and 17 cents lower than a month ago. The statewide average remains nearly a dollar higher than the national average of $4.30 per gallon.

Ephrata FD reports strong volunteer force, seeks long-term EMS funding solution
October 19, 2026 1 a.m.

Ephrata FD reports strong volunteer force, seeks long-term EMS funding solution

EPHRATA — Ephrata's Fire Department continues to provide service with a volunteer-based model that Chief Jeremy Burns said delivers significant value to taxpayers, but department leaders told the Ephrata City Council last week that future EMS funding needs, rising apparatus costs and aging equipment remain ongoing concerns.

Ephrata community development department highlights growth, housing projects during budget workshop
October 16, 2026 3 a.m.

Ephrata community development department highlights growth, housing projects during budget workshop

EPHRATA — Major construction projects, new housing developments and long-range planning efforts have kept the City of Ephrata community development department busy over the past year, with additional growth expected in 2027. During a budget workshop Tuesday, Ron Sell, Ephrata's community development director, updated the city council on completed projects, future developments and the department's priorities for the coming year. Sell said several major projects reached completion over the past year, including the new Grant County Jail, the Microtel Hotel and the Peachtree Drive road project.