Quincy Valley Medical Center board approves third phase of construction contract
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 2 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | November 7, 2023 3:54 PM
QUINCY — Quincy residents are beginning to hear and feel, if not yet see, construction on the site of the new Quincy Valley Medical Center.
The site has been cleared of three buildings, some trees and grass, and Tony Sanchez of Graham Construction said Monday that the next task is installing the pilings to support the new building, called geopiers.
“We drill eight to 10 feet (in) depth, fill them with rock and crush them down,” Sanchez said.
Chris Colley, also with Graham, said the building requires 294 geopiers, with installation taking seven to eight days. Sanchez said residents in the neighborhood will hear and feel the rumbling that comes along with the compacting.
“Beyond the geopiers, you’re going to start seeing footings and concrete (work at) the end of November, (early) December. You’re going to start seeing some formwork and concrete placement into December,” Sanchez said.
Graham managers on the project estimated the structural steel for the walls will start going up by the end of January.
The construction update came during a special hospital commission meeting to discuss approval of the last phase of the construction contract. It covers the bulk of the construction costs, and because of the way the contract is structured, will be the maximum cost the district will pay to build the building.
Joe Kunkle, the project manager for QVMC, said what’s called the “guaranteed maximum price” came in over the budget projection. Hospital commissioners approved a GMP of $40.16 million on a 4-0 vote. That’s compared to Graham’s original projection of $38.5 million.
The district had enough money in its contingency funds to cover the difference, Kunkel said, without requiring major changes in the project.
“Same number of beds, same number of exam rooms, same number of clinic rooms, all those parts and pieces. Same square footage,” Kunkel said.
Abram Jenks of the Klosh Group, which is overseeing the construction, said prices went up between the last estimate in August and the time the bids were opened in mid-October. Initially, the mid-October construction estimate was $40.8 million, Colley said. The project managers and QVMC officials reviewed the design to see if there were places to cut costs, Kunkel said.
“There were some easy things to find,” Colley said. “But there weren’t enough easy things to find.”
However, they did find some places to cut costs, Kunkel said. During the reviews managers and QVMC officials reduced the costs by about $627,000, Colley said.
“These were not easy meetings,” said QVMC Chief Executive Officer Glenda Bishop.
Construction managers had put some money aside in case prices increased, Jenks said. In addition, money was set aside during the design phase, and with the design phase over, that money could be applied to the construction budget.
“Does that cover the complete $1.6 (million) that we’re over (the construction estimate)? No, it does not cover it completely, but it comes close,” Jenks said.
The remaining money came from the project’s contingency fund for unexpected expenses. State mandates require a contingency of at least 5% on the project, Jenks said. Quincy’s contingency is still higher than that, he said, even with the construction cost going up. Both the contractor and the hospital are required to keep contingency funds, and between them the contingency is about 6.3%, he said.
“We are on budget, we have a GMP we are moving forward with, and we have our contingency,” Jenks said.
“There you go,” said board chair Randy Zolman after the board approved the GMP and applause broke out.
Bishop expressed gratitude to the construction managers and the work they’ve put in to get the project to the construction phase. The new hospital is scheduled to open in 2025.
“Joe told me at one point that there would be a lot of milestones along the way,” Bishop said. “Groundbreaking would be one of them, but he also told me this would be another one of them. And it feels like that to me today.”
Cheryl Schweizer can be reached via email at cschweizer@columbiabasinherald.com.
ARTICLES BY CHERYL SCHWEIZER
Classes, research results, latest tech at 2025 Washington-Oregon Potato Conference
KENNEWICK — Farmers can learn about new methods to fight insects and disease, water use and management, work rules and market conditions at the annual Washington-Oregon Potato Conference Jan. 28 to 30 at the Three Rivers Convention Center, 7016 Grandridge Blvd., Kennewick. Along with the classes and workshops – and a baked potato bar – the conference offers a trade show that fills not one but two buildings. The Washington Potato Commission, one of the sponsors, estimated there would be more than 165 exhibitors. The trade show opens Jan. 28, which is the first day of workshops and classes. Some classes provide continuing education credits that can be applied toward pesticide application license requirements.
Karlinsey hired as new Moses Lake city manager
MOSES LAKE — Robert Karlinsey, currently the city manager of Kenmore, Washington, has been hired as the new Moses Lake city manager. Moses Lake City Council members hired Karlinsey on a unanimous vote in a special meeting Jan. 21. Karlinsey will replace Mike Jackson, who had been the acting city manager following the resignation of Kevin Fuhr in July 2024. Fuhr retired for health reasons. Moses Lake Finance Director Madeline Prentice is the interim city manager.
REC Silicon job fair and support events planned
MOSES LAKE — Former REC Silicon employees laid off due to the closure of the Moses Lake facility can learn about available benefits and reemployment assistance at a “rapid response event” Friday. Two sessions are scheduled, 10 a.m. and 3 p.m., at the WorkSource Central Basin office, 309 E. Fifth Ave. In Moses Lake.