Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | July 18, 2024 1:15 AM

EPHRATA — The buildout of the Grant County Public Utility District fiber network should be complete by late October.

Fiber should arrive in Ruff by late August, and Wilson Creek by early October, according to a report at the July 9 PUD commission meeting. The initial build, which started in about 2008, will be complete with fiber installation in the Sagebrush Flat area and on Johnson Road Northwest, which should be complete by Oct. 31. 

Since the fiber network dates back nearly 20 years, crews are also working on maintenance and upgrades of the existing system. 

Utility district administrators have set a goal of hooking up 80% of available customers by the end of 2024. That’s called the take rate, and as of early July, it was at 75%.

The take rate ranges from 63% in Grand Coulee to 97% in Desert Aire. It’s 74% in Moses Lake, 75% in Ephrata, 80% in Quincy, 66% in Royal City, 65% in Soap Lake and 84% in Mattawa. 

The PUD does not provide direct service to retail customers. Access goes to ISPs, or internet service providers, who then sell to retail customers.

ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.