Work underway on some county roads, scheduled for others
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 10 months, 1 week AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 18, 2024 6:17 PM
EPHRATA — Drivers who frequently travel on Road 9 Northwest between Dodson Road and State Route 283 already know it, but drivers who don’t might want to find an alternate route while the road gets some work. Road construction also is planned for a section of Road H Southeast near Royal City, and upgrades to sidewalks and pedestrian ramps in the Larson area north of Moses Lake.
Grant County Engineer David Bren said it’s a case of trying to get as much road and bridge construction done in 2024 as possible, since there’s already a long list of projects for 2025.
“We’re going for it,” Bren said. “We already have $12.2 (million in road projects) already on the books for 2025. It is our hope to get as much of it done as we can.”
The section of Road 9 Northwest is being rebuilt, including replacing a bridge across an irrigation canal.
“They’re working on it. The old bridge was removed and the new bridge panels are already being put in,” Bren said. “They don’t play around - once they get to that point, they roll. And then you’ll see the road get reworked on either side (of the bridge).”
Project cost is about $2.1 million, about $1.89 million of it funded by the state.
“A good section of road being improved,” he said.
Road H Southeast also is scheduled for reconstruction.
“I don’t know when construction is going on that one yet,” Bren said. “I believe that one has a bridge on it as well. So it will be very similar to (Road 9 Northwest) where we’ll have to basically switch out the bridge and then do the road on either side of it.”
Project cost is about $1.8 million, with about $1.498 million from the state. In both cases, the remaining cost comes out of Grant County funds.
Construction crews also will be upgrading sidewalks in part of the Larson area, and upgrading pedestrian ramps at some intersections to comply with new American with Disabilities Act standards. Project cost is about $300,000, with the cost shared equally between Grant County and the Port of Moses Lake.
Bren said that while there’s a lot of bridge construction in 2024, most bridges in Grant County have stood the test of time.
“There’s some standouts that we need to replace, but our bridge system for Grant County, compared to other counties, is in really good shape. And I think part of that is that a lot of our bridges are old wood bridges, but our climate makes it so that our bridges don’t rot out,” he said.
“We’re fortunate because of our weather, that allows for the longevity of our old wood bridges.”
Grant County’s bridge system also is a testament to the work of the people who built them, Bren said.
“Some of the concrete bridges that were done almost 100 years ago, that are amazing works of art out there,” he said. “There are some amazing bridges that are still in use and doing great. Those before us did a good job of setting us up to where we are now. So we are reaping the benefits of our climate plus the hard work and effort of those before us doing things right. It makes a big difference.”
Cheryl Schweizer can be reached via email at cschweizer@columbiabasinherald.com.
ARTICLES BY CHERYL SCHWEIZER
Classes, research results, latest tech at 2025 Washington-Oregon Potato Conference
KENNEWICK — Farmers can learn about new methods to fight insects and disease, water use and management, work rules and market conditions at the annual Washington-Oregon Potato Conference Jan. 28 to 30 at the Three Rivers Convention Center, 7016 Grandridge Blvd., Kennewick. Along with the classes and workshops – and a baked potato bar – the conference offers a trade show that fills not one but two buildings. The Washington Potato Commission, one of the sponsors, estimated there would be more than 165 exhibitors. The trade show opens Jan. 28, which is the first day of workshops and classes. Some classes provide continuing education credits that can be applied toward pesticide application license requirements.
Karlinsey hired as new Moses Lake city manager
MOSES LAKE — Robert Karlinsey, currently the city manager of Kenmore, Washington, has been hired as the new Moses Lake city manager. Moses Lake City Council members hired Karlinsey on a unanimous vote in a special meeting Jan. 21. Karlinsey will replace Mike Jackson, who had been the acting city manager following the resignation of Kevin Fuhr in July 2024. Fuhr retired for health reasons. Moses Lake Finance Director Madeline Prentice is the interim city manager.
REC Silicon job fair and support events planned
MOSES LAKE — Former REC Silicon employees laid off due to the closure of the Moses Lake facility can learn about available benefits and reemployment assistance at a “rapid response event” Friday. Two sessions are scheduled, 10 a.m. and 3 p.m., at the WorkSource Central Basin office, 309 E. Fifth Ave. In Moses Lake.