Adams Co. planning broadband infrastructure expansion
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 6 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | May 29, 2024 2:10 AM
RITZVILLE — Construction could start as early as August on a project to bring fiber optic cable to the Ritzville and Lind areas. Adams County Public Works Director Todd O’Brien said fiber installation in the two cities would be the first phase of a two-phase project. The second phase will be the addition of fiber in an area south of Othello.
“Our designer is putting together bid specifications,” O’Brien said. County officials want to advertise for bids in June, with bids opened and the contract awarded in July. If all goes well, construction will start sometime in August.
“That’s kind of the general goal right now,” he said.
O’Brien said crews will be installing fiber within the Rtizville and Lind city limits. Once the fiber backbone is completed, customers will go through a service provider to hook up to the system, he said.
Adams County was awarded a $10.3 million grant from the Washington Broadband Office for both phases.
There’s still some work to be done in the Ritzville-Lind area, O’Brien said, in the form of final approval of some construction permits. The permitting process is still ongoing on Othello, with permits required to work around railroad tracks, state highways and irrigation canals, among other things.
“We’re still working through the permit process on that,’ O’Brien said.
Most of the fiber cable will be aerial, but some places will require underground installation, O’Brien said. The grant includes money to install the underground conduit at no charge to the property owner. But permission is required from property owners first, he said.
If construction begins in the late summer or early fall, the goal would be to finish the project as soon as possible, but that’s subject to fall and early winter weather conditions, he said. That may push the completion of the first phase to spring 2025. County officials hope to be able to start the Othello area phase by spring 2025.
O’Brien said county officials want to apply for a second grant to expand the network into rural areas of Adams County, once the funding becomes available.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
North Cascades Highway closed, possibly for the winter
WINTHROP — Snow slides along the North Cascades Highway closed the road early Thanksgiving evening, but Washington Department of Transportation officials aren't sure yet whether the road will be closed for the winter.
Water, sewer, parks improvements in Othello capital projects plan
OTHELLO — Upgrades to the heating-cooling system at Othello City Hall, a new shelter in Lions Park and upgrades to sections of 14th Avenue are among the possible projects for 2027 included in the city's six-year capital facilities plan.
Construction could mean temporary closure of South Pioneer Way intersection next spring
MOSES LAKE — A new roundabout is tentatively scheduled for construction at the intersection of Yonezawa Boulevard and South Pioneer Way in spring 2027.