ROAD REPORT: Westshore Dr. and Othello roundabout updates

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 10 months, 4 weeks AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | May 9, 2025 1:25 AM

MOSES LAKE — The rebuilding of a 2.1-mile section of Westshore Drive west of Moses Lake has reached the sidewalk stage. 

Curbs have been poured along the route and construction crews were adding a base layer for the sidewalks Thursday. A power shovel and front loader dumped rock along the sidewalk course, which was spread partly by the shovel and partly by hand. Once that’s done the material is compacted.  

The work is affecting travel on Westshore; a few drivers were using it on Thursday morning, negotiating around construction equipment. There are detours along Road E Northeast and Road F Northeast for most of the project’s length.  

The road itself was excavated and the old asphalt removed, and the rebuild has reached the stage of a completed base layer. The project began in early March and is scheduled for completion in mid-July. Total project cost is about $3.63 million.  

The sections of Westshore Drive immediately north and south of the construction zone have already been repaved and have sidewalks. This project connects the sections and gives Westshore sidewalks along most of its length. 

After some uncertainty, a roundabout will be coming to Othello this summer. 

“The roundabout at (state Route) 26 is a go,” wrote Sebastian Moraga, communications consultant for the Washington Department of Transportation, in response to an email from the Columbia Basin Herald. 

Construction is scheduled to begin in early August and last two to three months, Moraga said. 

The roundabout will be at the intersection of SR 26 and South First Avenue in Othello. The existing intersection doesn’t allow traffic across SR 26, and access to State Route 24 requires a detour down East Wahluke Street.  

Ellen Guisfredi, DOT assistant project engineer, told Othello City Council members in December that the design takes into account the substantial truck traffic at that intersection. 

“It will have a fully mountable truck apron as a lot of heavy traffic and very large trucks come through this intersection,” she said. “It is designed for larger vehicles because of the large truck movement.” 

The project will affect drivers trying to access SR 26. 

“The majority of (traffic control) will be alternating one-lane traffic with temporary signals on state Route 26,” Guisfredi said. “We won’t be detouring highway traffic, but we will be detouring traffic that is on city and county roads. Any traffic attempting to enter (SR) 26 at this intersection will be directed to use detour (routes).”    


ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.