Hansen overpass to be replaced
NANCE BESTON | Hagadone News Network | UPDATED 1 month, 2 weeks AGO
MOSES LAKE — Hansen Overpass will be replaced this summer, with project completion planned for December 2026, according to the Washington State Department of Transportation.
The bridge closed Jan. 17 because of safety concerns caused by the deterioration of the bridge deck and pier caps. According to WSDoT, because of the level of deterioration, there is no temporary fix to reopen the road. Detours will remain in place until the new bridge is complete.
The project design begins this month. In June, the old bridge is planned to be demolished. Construction is planned to begin in July. The new bridge is planned to be open to traffic in December.
The City of Moses Lake released a statement of appreciation for the state’s assistance in moving forward with a solution to the overpass.
“While this is a state-owned bridge, we know the closure has created real challenges for our community – impacting residents commuting to work, students who rely on school bus transportation and access to essential services,” reads the statement.
The bridge was built in 1958 and connects the north and south sides of Interstate 90. It was subsequently refurbished in 1992. Repairs for deck deterioration were completed in 2023 after chloride contamination was discovered. More frequent inspections were scheduled afterwards.
During Media Day at the state Capitol, Sen. Marko Lias, D-Edmonds, who chairs the Transportation Committee in the Washington Senate, said the issues associated with the bridge were caused by a variety of factors, including improper sealing of the bridge surface. He added that bridges throughout the I-90 corridor were being examined to ensure similar problems weren't present.
ARTICLES BY NANCE BESTON
1 arrested after Highway 17 stop; detectives recover fentanyl, firearms
MOSES LAKE — The Moses Lake Street Crimes Unit conducted a traffic stop on Highway 17 near Randolph Road and executed a search warrant Friday morning as part of an ongoing narcotics investigation.
4th-year drought declaration in WA, subtle effects in the Columbia Basin
EPHRATA — Washington’s fourth straight year of drought is expected to hit some regions hard, but in Grant and Adams counties, the impacts will look different – quieter, less visible and centered underground. Statewide, the Department of Ecology issued an emergency drought declaration after a warm winter left Washington with about half its usual snowpack, raising concerns about low summer streamflows, stressed fish populations and heightened wildfire risk. Seven of the past 10 years have included drought somewhere in the state. “If you look at our mountains, the challenge we are facing is clear,” Gov. Bob Ferguson said during a press conference Wednesday. “We’re taking emergency action to protect fish, farmers and communities across Washington.”
Sleep Diagnostic Center to close after doctor’s sentencing
MOSES LAKE — The Central Washington Sleep Diagnostic Center announced it will be closing its doors effective April 30. This includes locations in Moses Lake, Spokane Valley, Brewster and Wenatchee. The announcement follows the March 25 guilty plea from Dr. Eric Edward Haeger, 57, in United States District Court to adulterating and misbranding medical devices with the intent to defraud or mislead, according to a statement from the U.S. Attorney’s Office. “The adulterations by Dr Haeger show a dangerous disregard for the safety of his patients,” Washington Attorney General Nick Brown said in a statement. “This is a win for patient safety, for protecting public dollars from fraud, and for ensuring citizens of Washington get necessary healthcare. This case exemplifies the great work our team is doing in collaboration with our federal partners to fight fraud and protect Washingtonians.”