Hansen Road bridge construction to begin late June, early July
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 8 months, 2 weeks AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 11, 2026 3:28 PM
MOSES LAKE — Demolition of the Hansen Road overpass will begin in late June or early July. Chris Keifenheim, North Central Region administrator for the Washington State Department of Transportation, said DOT officials will be monitoring the Hiawatha Road overpass to ensure it stays open during construction.
“I think you’re all aware we were able to get the funding to replace the bridge,” Keifenheim said. “You’ll see bridge construction happening out there from July until about the end of December. Right now, our plan is to finish around the first of the year, the end of 2026, the (beginning) of 2027.”
Keifenheim gave an update on the bridge to the Moses Lake City Council at its regular meeting Tuesday.
The bridge was closed in January after inspectors found considerable damage to the bridge's deck and supporting pillars. The closest alternate route for residents of Mae Valley and the area south of Interstate 90 is Hiawatha Road, which required repairs to the bridge deck in early February.
“That bridge has seen some deterioration as well. We are monitoring that closely with the intent to keep that bridge in full operation during the detour,” Keifenheim said. “We did do some fluoride testing on that as well, and it is seeing some deterioration similar to that at Hansen, but just a little bit behind.”
Money was included in the Hansen Road project for repairs to Hiawatha Road if necessary, he said.
The new Hansen Road bridge will be designed with central columns as the main support, which is slightly cheaper and easier to maintain, he said. Demolition and some of the work on the new bridge will require closures of one lane in each direction on I-90, he said.
Mayor Dustin Swartz said the Hansen Road intersection could use additional work.
“One that comes to mind is where you added, like a half-roundabout on the south side,” Swartz said. “Will that be put in in a more permanent fashion?”
Keifenheim said the only work scheduled for this contract is the bridge replacement.
“I fully agree that there are some improvements, both on the north and south side, that would be beneficial that would be beneficial to the operation of that intersection, the safety of that intersection, but that’s not the funding we have,” he said. “This is strictly to replace the current bridge.”
In answer to a question from council member Victor Lombardi, Keifenheim said the new bridge is projected to last about 75 years.
“With good maintenance and preservation, we could expect them to last even longer than that, but that’s part of the reason you’re seeing this deterioration on some of these bridges now is that we just haven’t been able to keep up with the maintenance and preservation we need to with the funding that we have,” Keifenheim said.
Council member Don Myers said the city owns a fire truck that can’t cross the existing bridge when it’s fully loaded with water. He asked if the new bridge would be able to handle that weight. Keifenheim said he didn’t know.
“All regular load ratings should be able to cross the bridge,” Keifenheim said. “I’ll double-check on that.”
Neighborhood information meeting
Hansen Road bridge construction
6:30 p.m. March 18
Pillar Rock Grill, 1373 Road F.2 NE
ARTICLES BY CHERYL SCHWEIZER
Goal is late 2028, early 2029 opening for Port of Quincy power generation project
QUINCY — A Port of Quincy project for its own electrical generation facility is projected to open in 2029 at the latest.
Mattawa may eliminate one PD position, drop SRO
MATTAWA — The Mattawa City Council and city officials are discussing eliminating one Mattawa Police Department position and not renewing the contract with the Wahluke School District for a school resource officer. Wahluke Superintendent Andy Harlow said WSD officials and the Wahluke School Board are looking for alternatives in light of that discussion. "Right now, we want to work with the chief and the mayor and the council to get this figured out. But at this point, based on what we have, we're considering all options," Harlow said. Mayor Maria Celaya said in a text message Mattawa City Council members are discussing those options.
Consumers asked to use caution to avoid charity scams
MOSES LAKE — Christmas is a season of giving, and there are plenty of worthy causes out there – but there are scammers out there working to divert some of that generosity to themselves. In addition, when it comes to defrauding people, scammers aren't content to wait until the holiday season. Scammers will latch on to any incident, any natural disaster in their attempts at fraud. "When there's a disaster such as the Spokane wildfires or an incident that affects a community, such as the line of duty deaths of the two sheriff's deputies in the Spokane area, fraudsters may take may choose to take advantage of people's kindness by creating fake charity accounts," said Kyle Foreman, public information officer for the Grant County Sheriff's Office.