New hangar, fire main under construction at Port of Moses Lake

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 month, 1 week AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 24, 2026 3:00 AM

MOSES LAKE — Port of Moses Lake officials are taking advantage of a construction project at Grant County International Airport to improve firefighting service to the west section of the port’s business property. Port commissioners approved paying about $312,600 to Freeman Holdings, the owners of Million Air, for the port’s portion of a bigger water main for fighting fires. 

“For our purposes, we wanted the fire line to be larger than what we intended to put in for their needs. We have a reservoir (on the east side of the field) with a pumping station, and it services both sides of the airfield,” said Carol Crapson,  the port’s director of real estate. “It goes over to Genie, to Chemi-Con, and it also comes (toward the west side of the field) and services the existing hangers. Now Million Air is making a connection to that line, but they really only needed 12 inches to service their needs. And in order to continue it and have the pressure at the end, we needed a 20-inch main, so we paid for the difference.” 

The new Million Air hangar is under construction on the west side of the terminal, with portions of the exterior skeleton installed. The construction includes the installation of the water main for firefighting services.  

Kim DeTrolio, the port’s director of finance and administration, said the company’s original plan was to install a water main big enough to fight a fire at the hangar. That wouldn’t work for the rest of the port’s undeveloped property on the west side. That requires a 20-inch main.  

The bigger water main is for firefighting only, DeTrolio said. Any development on the west side will be required to get water and sewer hookups from the city of Moses Lake, she said. 

The west side industrial property was opened up in 2021, after port officials built a road connecting their property with state Route 17. The road also connects to Road 10 Northeast. 

The west side expansion was necessary because the industrial land on the port’s east side is already taken, said former port Director Don Kersey in a 2020 interview.  


ARTICLES BY CHERYL SCHWEIZER

Othello man pleads not guilty to vehicular homicide charges
May 4, 2026 12:45 p.m.

Othello man pleads not guilty to vehicular homicide charges

RITZVILLE — An Othello man has pleaded not guilty to three counts of vehicular homicide in connection with a collision that killed three 15-year-old girls last week. Presiliano Perez-Pineda, 19, entered a not guilty plea at an Adams County Superior Court Monday morning. He is being held on $1 million bail. The trial was set for June 16, with a pretrial hearing scheduled for June 8. Perez-Pineda also was charged with leaving the scene of a collision. The charges stem from the collision about noon on April 26 on West Bench Road about one mile south of Othello.

Hermiston man sentenced in 2022 murder of Moses Lake woman
May 2, 2026 2:43 p.m.

Hermiston man sentenced in 2022 murder of Moses Lake woman

EPHRATA — A Hermiston, Oregon man has been sentenced to 20 years to life in prison following his guilty plea in the March 2022 murder of a Moses Lake woman.

Delays anticipated at Othello intersection as roundabout construction begins
May 2, 2026 2:40 p.m.

Delays anticipated at Othello intersection as roundabout construction begins

OTHELLO — Construction begins Monday on a new roundabout near Othello, which will mean the start of flagger-controlled traffic at the intersection of State Route 17 and West Cunningham Road.