Tentative opening date set for new Quincy Aquatic Center

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 hour, 8 minutes AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | May 20, 2026 6:06 PM

QUINCY — Not only a new swimming pool but a new splash pad will be coming to Quincy this summer. Russ Harrington, Quincy parks and recreation director, said there are tentative opening dates for the new Quincy Aquatic Center and the park that includes the splash pad, although it may not be ready at the same time as the park.

“We’re getting close,” Harrington said.

The splash pad is one of the amenities in the new park at the intersection of Sixth Avenue and E Street Northeast. The park’s playground toys have been installed; Harrington said ground cover is the last piece for those toys, and it’s scheduled for installation within the next few days. The playground toys should be ready for use by June 1.

The splash pad requires inspection by the Washington Department of Health, Harrington said. That may take a little longer.

“There isn’t a lot left to do, but there’s a little bit left to do,” he said.

The splash pad is something entirely new for Quincy; previously the land was an undeveloped lot. Quincy has had a pool for a half-century or more, but it’s getting a completely new one. The planned date for opening is June 26-28.

Harrington emphasized that’s the target, but a target is all it is right now.

“We don’t have a hard and fast opening date,” he said.

There is still some work to be done on the pool, Harrington said, but getting the pool finished is only half the job. A new pool requires training for new lifeguards and retraining for experienced ones.

“We’ve got to train almost 30 new lifeguards,” Harrington said. “There’s a lot that’s going to be packed into the next five weeks.”

About 35-45 lifeguards will be needed for a full staff, he said.

Swimming lessons are tentatively scheduled to begin July 6. Signups for lessons will be open sometime in the next two weeks.

Construction of the pool follows the establishment of the Quincy Valley Regional Parks District, which has the same boundaries as the Quincy School District minus the Douglas County portion. The district also will own and operate the indoor arena known as the QPlex. That’s still in the design phase.

Chervenell Construction, Kennewick, was awarded a $15.7 million contract for pool construction.

The new pool design features a separate lap pool and water slide array. The lap pool will have a one-meter diving board, a rope swing and a climbing wall.

Three water slides have been installed, two that are 220 feet long and another that’s 190. One of the 220-foot slides is enclosed. They do not empty into the pool.

There’s a 48-inch height limit on the slides, and it will be strictly enforced, Harrington said.

“These are way different slides than the ones we’ve had in the past,” he said.

The zero-depth end of the pool has an elaborate toy for children who don’t make the height limit, with a triple slide, water spray features, water toys and a big bucket dumping water periodically.

“Everything is going to be fun in there,” Harrington said.


    The new Quincy Aquatic Center will have an entirely new set of waterslides.
 
 


ARTICLES BY CHERYL SCHWEIZER

May 20, 2026 6:13 p.m.

No deficiencies in Wahluke School District audit

MATTAWA — An audit of the Wahluke School District didn’t find any deficiencies in the district’s federal program management or its financial reporting. It was the second straight deficiency-free audit for the district. Wahluke Superintendent Andy Harlow said that was due to WSD’s financial staff. “I continue to be impressed with (Gabriela) Chacon, our finance director, and her team’s hard work, growth and commitment to implementing and sustaining fiscal systems,” Harlow wrote in response to an email from the Columbia Basin Herald

Tentative opening date set for new Quincy Aquatic Center
May 20, 2026 6:06 p.m.

Tentative opening date set for new Quincy Aquatic Center

QUINCY — Not only a new swimming pool but a new splash pad will be coming to Quincy this summer. Russ Harrington, Quincy parks and recreation director, said there are tentative opening dates for the new Quincy Aquatic Center and the park that includes the splash pad, although it may not be ready at the same time as the park. “We’re getting close,” Harrington said. The splash pad is one of the amenities in the new park at the intersection of Sixth Avenue and E Street Northeast. The park’s playground toys have been installed; Harrington said ground cover is the last piece for those toys, and it’s scheduled for installation within the next few days. The playground toys should be ready for use by June 1.

Mobile home destroyed in early-morning fire
May 20, 2026 3:20 p.m.

Mobile home destroyed in early-morning fire

MOSES LAKE — A mobile home north of Moses Lake was destroyed by fire early Wednesday morning. Grant County Fire District 5 Battalion Chief Sean Killion said the fire was reported at about 4:20 a.m. on Broad Street Northeast, off Airway Drive Northeast. “It was vacant,” Killion said, and no one was injured. The trailer was fully engulfed when firefighters arrived, but no nearby structures were damaged, he said. The trailer was a total loss. Firefighters were on the scene about 90 minutes, he said. “The cause of the fire is undetermined, per the fire marshal,” Killion said.