Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | November 21, 2026 2:39 PM

QUINCY — A Port of Quincy project for its own electrical generation facility is projected to open in 2029 at the latest. 

"As we move along, we're still looking to have power at the tail end of 2028, first part of 2029," said Port Commission Chair Curt Morris. 

The port is working with a Native American company, Colusa Indian Energy, to build a generating facility on port property in the northeast part of Quincy. Port officials provided an update on the project at a community meeting Nov. 19. 

The project originally was announced in February. Morris said there have been some changes, especially in the power source, in the light of current state regulations.  

"The absolute best path is natural gas. But until the state allows that to happen, we need to do something. The second-best path is using recycled plastics," Morris said. 

The plastics will be used for the generating source, but they won't be burned, he said. 

"We went through that (in the presentation) because you don't burn them. People think when you're talking about the use of plastic for fuel, that you're burning it," Morris said. "But you're not burning it. You're decomposing it faster than it would decompose in a landfill. Right now, all kinds of plastic go to the landfills, and plastic takes anywhere from like five to 500 years to decompose. This is doing basically that same process, just a million times faster." 

That will meet state environmental standards, he said.  

"The thought is, we'll use plastics, and they're already pelletized to come into our facility. we'll run it through a reactor that decomposes them into oil, gas, and a small residue that you just get rid of," he said. "But it's all internal, and it's not going out into the air. And then the gas you shoot through the power plant to turn the generators." 

Building the facility requires a few intermediate steps, including upgrades to the port's rail lines in the area. The raw materials for generation will be delivered by rail, Morris said. 

"We've got to get the rail component taken care of. They are starting to build the first phase of the rail – construction will start November 30th. We're working to design the second phase," Morris said. 

The first phase of rail construction, Morris said in an earlier interview, will double the amount of track at the port's intermodal facility. The port has received federal funding for the first phase, he said. Funding for the second phase is pending.   

The second phase will extend the rail lines to port-owned property across Road O Northwest.  Morris said that while it would be more efficient to have both phases of the rail project completed, the electrical generation facility can proceed with it. 

"We can unload the pellets in our intermodal yard once we get phase one done, and then we can truck them around the plant," he said 

While the power generated by the process is more expensive than hydropower, Morris said port officials believe it will be competitive on the market. Because plastics are being used as a generation source, the process will be exempt from some state taxes, he said. 

The first customers are projected to be existing power distributors, such as the Bonneville Power Administration and the Grant County Public Utility District. But over time, port officials think more of the power will be used by its own customers, Morris said.  

The facility will be built with expansion in mind, Morris said. 

"It will ultimately take that that 150 acres, not to start with, but (there's) plenty of room to expand because to expand is very simple. You just add another reactor type deal for pellets," Morris said. 

The tentative goal is to break ground in spring 2027, he said.  

"In a perfect world," Morris said. "I'd love to see (equipment) out there starting. Then everything will really start moving, because people will be able to see with their own eyes that it's happening, and by that time we'll have it priced out as well." 


    The Port of Quincy will be breaking ground Nov. 30 on its rail expansion project.
 
 


ARTICLES BY CHERYL SCHWEIZER

Goal is late 2028, early 2029 opening for Port of Quincy power generation project
November 21, 2026 2:39 p.m.

Goal is late 2028, early 2029 opening for Port of Quincy power generation project

QUINCY — A Port of Quincy project for its own electrical generation facility is projected to open in 2029 at the latest.

Mattawa may eliminate one PD position, drop SRO
November 21, 2026 1:10 p.m.

Mattawa may eliminate one PD position, drop SRO

MATTAWA — The Mattawa City Council and city officials are discussing eliminating one Mattawa Police Department position and not renewing the contract with the Wahluke School District for a school resource officer. Wahluke Superintendent Andy Harlow said WSD officials and the Wahluke School Board are looking for alternatives in light of that discussion. "Right now, we want to work with the chief and the mayor and the council to get this figured out. But at this point, based on what we have, we're considering all options," Harlow said. Mayor Maria Celaya said in a text message Mattawa City Council members are discussing those options.

Consumers asked to use caution to avoid charity scams
November 20, 2026 3 a.m.

Consumers asked to use caution to avoid charity scams

MOSES LAKE — Christmas is a season of giving, and there are plenty of worthy causes out there – but there are scammers out there working to divert some of that generosity to themselves. In addition, when it comes to defrauding people, scammers aren't content to wait until the holiday season. Scammers will latch on to any incident, any natural disaster in their attempts at fraud. "When there's a disaster such as the Spokane wildfires or an incident that affects a community, such as the line of duty deaths of the two sheriff's deputies in the Spokane area, fraudsters may take may choose to take advantage of people's kindness by creating fake charity accounts," said Kyle Foreman, public information officer for the Grant County Sheriff's Office.