Port of Moses Lake awards $31.7 million rail contract
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 hours, 31 minutes AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | October 27, 2026 3:25 AM
MOSES LAKE — After 20 years of planning a route, obtaining funding and getting rights-of-way, construction on the railway connection between the Port of Moses Lake and the Columbia Basin Railroad should start before the end of the year.
"On or about 1 December is when I expect to break ground," said Anne Reese of Rock Project Management, Renton. "The contractor is hoping to mobilize prior to Thanksgiving, but worst case, it'll be right after Thanksgiving."
Completion is projected for early spring 2028, she said.
Port commissioners approved a $31.75 million contract with Martinus Rail LLC North America at the regular meeting Monday.
"That may be the biggest single contract we've ever approved," said Commissioner Kent Jones.
He was surprised, Jones said, that all six bids were relatively close to each other.
"And so low," said Finance and Administration Director Kim Detrolio.
"That's a good thing. I was pleasantly surprised," Jones said.
It's the first phase of a multi-phase project. It's been a long time coming, said Facilities Director Milton Miller.
"We've been working on this rail project for the last two decades," he said.
Milton Miller said it's both rehabilitation and a new build.
"It's going to be five miles of new track, roughly 1,000 feet off the Wheeler corridor, then rehabbing the line from (near Kinder Road Northeast) out to the airport," Miller said. "Once that line is complete, then we can abandon the line downtown."
The new line will provide rail service from the port via the CBRR to its junction with the BNSF tracks at Connell. That connection will allow products from the port and along the rail line to be shipped nationwide.
Miller said in earlier interviews that federal regulations prohibit abandoning the existing line until a new line is completed. That will eliminate the tracks that cross SR 17 and wind through town along the lakeshore, cross West Broadway Avenue and run in front of Montlake Park.
The new line will require new rail crossings, including East Wheeler Road, and also includes upgrades to existing rail crossings, Miller said.
The port received about $33 million from state and federal sources, but inflation raised the project cost. Port Executive Director Dan Roach said in an earlier interview that port officials were looking for ways to pay any remaining costs. They got some help from Senator Judy Warnick, who sponsored a bill to allow the port to increase its indebtedness level.
With that authority, Detrolio said port officials are looking at funding opportunities, including the possible issuance of a construction bond.
"Our bond team has gotten together several times starting in March, and we continue that process, hopefully in January, to be able to fund this next rail project," Detrolio said.
ARTICLES BY CHERYL SCHWEIZER
Stoke Space looking for first launch in 2027
MOSES LAKE — The owners of Stoke Space Technologies are planning the first launch of the company's reusable space vehicles in 2027. "As early as we can do it next year," said Stoke Space Chief Executive Officer Andy Lapsa. Lapsa and Chief Operations Officer Jonathan Lund attended the Port of Moses Lake commission meeting Monday to update commissioners on the company's progress, and to thank port officials and commissioners for the support they've received since they arrived in Moses Lake in 2021.
Port of Moses Lake awards $31.7 million rail contract
MOSES LAKE — After 20 years of planning a route, obtaining funding and getting rights-of-way, construction on the railway connection between the Port of Moses Lake and the Columbia Basin Railroad should start before the end of the year. "On or about 1 December is when I expect to break ground," said Anne Reese of Rock Project Management, Renton. "The contractor is hoping to mobilize prior to Thanksgiving, but worst case, it'll be right after Thanksgiving."
Moses Lake man arrested for allegedly selling stolen property
MOSES LAKE — A Moses Lake man was arrested and booked on suspicion of selling stolen property and possessing a stolen vehicle after Grant County Sheriff's deputies interrupted the sale of a stolen pickup Friday. Joseph Vela, 39, was also arrested on an outstanding felony warrant, said Kyle Foreman, GCSO public information officer. Who actually stole the truck is still under investigation, Foreman said. Deputies received a report of a stolen vehicle at about 6:30 p.m. Friday, Foreman said. They found a truck, a 2004 Ford F-150, being hauled on a trailer in the 2000 block of Road L Northeast. The truck was confirmed stolen.